ANSI/NETA ATS · Before Energization

New Service Commissioning & Acceptance Testing

A new electrical service gets energized once. Whatever was miswired, under-torqued, mis-set, or damaged in shipping goes live with it — unless acceptance testing catches it first.

New switchboard interior with breakers and conductors

Before You Energize, Prove It

Commissioning is the structured inspection and testing of new switchgear and services before first energization, performed to ANSI/NETA ATS standards, so the system you turn on is the system that was designed.

Catching deficiencies at this stage matters: the installer is still on site, the equipment is under warranty, and corrections don't require an outage at an operating facility.

What's Included

  1. Visual and mechanical inspection — equipment condition, clearances, barriers, labeling, and comparison against drawings and nameplates.
  2. Torque verification — bus and lug connections checked to manufacturer specifications; loose connections are a leading cause of early failures and hot spots.
  3. Insulation resistance testing — bus, feeders, and windings megger-tested to confirm insulation integrity before power is applied.
  4. Contact resistance testing — breaker and switch contacts measured (DLRO) to catch damaged, dirty, or misaligned contacts.
  5. Circuit breaker testing — primary and/or secondary injection testing, with trip unit settings applied from the coordination study.
  6. Ground-fault protection testing — NEC 230.95(C) requires the GFPE system to be performance tested when first installed, with a written record available to the inspector. We perform the test and provide the record.
  7. Arc energy reduction verification — if your service has breakers rated 1,200 amps or higher, NEC 240.87 requires an arc energy reduction method. We verify the maintenance switch / RELT function works and document it.
  8. Phasing and grounding checks — phase rotation, phasing between sources, and ground system verification.
  9. Report and deficiency list — a complete acceptance test report with every result documented, plus a clear list of deficiencies for correction before or after energization.

The Baseline Matters Later

Commissioning records become the baseline for your maintenance program. Future test results are compared against them to spot deterioration — this is the foundation of the documented maintenance program NFPA 70B calls for, and the paperwork your insurer and safety auditors will ask for.